DevFeeFinder
TransportationSet by plan area fee

Plumas Lake Specific Plan published total (2,000 sf production home)

Levied by Yuba County and the agencies it lists — County, OPUD, MJUSD, PLESD, WHSD, RD 784, TRLIA, SYTIA, LFPD on new development in Yuba County (unincorporated). Authorized under the Mitigation Fee Act - Gov. Code Sec. 66000 et seq. (specific plan area fee). Collected other: split line by line — five lines "Prior to BP issuance", six lines "Prior to BP final".

What one house pays

$48,656

This fee is not in Yuba County (unincorporated)'s published figure. This site publishes a home outside any plan area, and this charge applies only in Northern PLSP. The amount shown is what it costs a house that is there.

Total one-time fees here
$62,832
Adjustment
Adjusts yearly · ENR construction cost index · July
what the document says

annual, ENR-CCI (average of the San Francisco and 20-Cities Construction Cost Index), each July 1 — County Chapter 13.50 lines only; the other agencies' lines carry no escalator on this document (not stated)

Next expected change
1 Jul 2027

The record

Why it exists

“To develop, at no cost to the existing residents and property owners outside of the PLSP/NASA area, new infrastructure and other facilities which exclusively serve the PLSP/NASA area.”

Annual Countywide Capital Facilities Fee Report FY 2024-2025, Exhibit A, Fund 2620, p.4 · source document ↗
What it pays for

“PLSP (2620) | Capital Improvement Projects | ($904,491.70) | Plumas Lake Interchange Project”

Annual Countywide Capital Facilities Fee Report FY 2024-2025, Exhibit B — Impact Fee Fund Detail, p.7 · source document ↗
Where it applies

“Northern PLSP Production Home, Fees Effective July 1, 2026: Includes the North Arboga Study Area (NASA) | 2,000 sq. ft. production home on a typical finished lot, with sprinklers.”

Northern PLSP Production Home estimate, fees effective 2026-07-01, heading · source document ↗
When it was adopted

2014 — the PLSP/NASA component only (Fund 2620); the published estimate itself is a compilation with no enactment date

“2620 | PLSP/NASA | BOS Resolution 2014-48 | To develop, at no cost to the existing residents and property owners outside of the PLSP/NASA area, new infrastructure and other facilities which exclusively serve the PLSP/NASA area.”

Yuba County Annual Countywide Capital Facilities Fee Report FY 2024-2025, Exhibit A, p.4 · source document ↗
Who adopted it

“2620 | PLSP/NASA | BOS Resolution 2014-48 | To develop, at no cost to the existing residents and property owners outside of the PLSP/NASA area, new infrastructure and other facilities which exclusively serve the PLSP/NASA area.”

Yuba County Annual Countywide Capital Facilities Fee Report FY 2024-2025, Exhibit A, p.4 · source document ↗
When it is paid

other: split line by line — five lines "Prior to BP issuance", six lines "Prior to BP final"

“Fee Type | Amount | Time of Payment | Entity | Notes ... Water Fee | $9,058.00 | Prior to BP issuance | OPUD ... PLSP Traffic Impact Fee | $7,241.76 | Prior to BP final | County”

Northern PLSP Production Home estimate, fees effective 2026-07-01, table header and rows · source document ↗
Who collects it

per line, as named in the estimate's "Entity" column

“Levee Impact Fee-Plumas Zone | $13,202.00 | Prior to BP final | TRLIA | *See Note ... Fire Impact Fee | $2,440.00 | Prior to BP final | LFPD | Based on $1.22/sq. ft.”

Southern PLSP Production Home estimate, fees effective 2026-07-01, Entity column · source document ↗
Who is exempt

“12. Development Impact Fees may not be collected on buildings accessory to a legally established residence, as determined by the Community Development and Services Agency's Planning Director. 13. Development Impact Fees and Drainage Fees shall not be collected on governmental facilities.”

Yuba County Code ch. 13.50, Countywide Development Impact Fees, s. 13.50.030(a)(12)-(13), effective July 1, 2015 · source document ↗
Credits and offsets

“Credits and Reimbursements – Dedicated Facilities. Upon satisfactory completion of a public facility or improvement upon which the Development Impact Fees and/or Drainage Fees are based ... and dedication of said facility or improvement to the County, and acceptance by the County, owner of said improvement shall receive credit against applicable Development Impact Fees and/or Drainage Fees.”

Yuba County Code ch. 13.50, s. 13.50.060(c), effective July 1, 2015 · source document ↗

Every published rate

Every rate below applies to single-family detached.

ComponentBasisEffectiveAmount
Northern PLSP
School Impact Fee ($5.38/sf) - Marysville Joint USD per DU 1 Jul 2026 $10,760
the line this rate was read from

“School Impact Fee - Marysville Joint Unified | $10,760.00 | Prior to BP issuance | MJUSD | Based on $5.38/sq. ft. (effective 5/11/2026)”

Northern PLSP Production Home estimate, fees effective 2026-07-01, fee table · source document ↗
Sewer Fee (treatment + collection) - OPUD per DU 1 Jul 2026 $10,342
the line this rate was read from

“Sewer Fee | $10,342.00 | Prior to BP issuance | OPUD | treatment and collection”

Northern PLSP Production Home estimate, fees effective 2026-07-01, fee table · source document ↗
Water Fee (1 inch meter, sized for fire flow) - OPUD per connection 1 Jul 2026 $9,058
the line this rate was read from

“Water Fee | $9,058.00 | Prior to BP issuance | OPUD | At 1'' meter to reach fire flows”

Northern PLSP Production Home estimate, fees effective 2026-07-01, fee table · source document ↗
PLSP Park Impact Fee - OPUD per DU 1 Jul 2026 $8,814
the line this rate was read from

“PLSP Park Impact Fee | $8,814.00 | Prior to BP final | OPUD”

Northern PLSP Production Home estimate, fees effective 2026-07-01, fee table · source document ↗
PLSP Traffic Impact Fee - County plan-area per DU 1 Jul 2026 $7,242
the line this rate was read from

“PLSP Traffic Impact Fee | $7,241.76 | Prior to BP final | County”

Northern PLSP Production Home estimate, fees effective 2026-07-01, fee table · source document ↗
Fire Impact Fee ($1.22/sf) - Linda FPD per DU 1 Jul 2026 $2,440
the line this rate was read from

“Fire Impact Fee | $2,440.00 | Prior to BP final | LFPD | Based on $1.22/sq. ft.”

Northern PLSP Production Home estimate, fees effective 2026-07-01, fee table · source document ↗
Southern PLSP
School Impact Fee - Plumas Lake ESD ($5.09/sf) per DU 1 Jul 2026 $10,180
the line this rate was read from

“School Impact Fee - Plumas Lake Elementary | $10,180.00 | Prior to BP issuance | PLESD | Based on $5.09/sq. ft. for CFD 1 Area”

Southern PLSP Production Home estimate, fees effective 2026-07-01, fee table · source document ↗
per DU 1 Jul 2026 $4,300
the line this rate was read from

“School Impact Fee - Wheatland HS | $4,300.00 | Prior to BP issuance | WHSD | Based on $2.15/sq.ft. (effective 5/20/2026)”

Southern PLSP Production Home estimate, fees effective 2026-07-01, fee table · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.