DevFeeFinder
Public safetySet by city fee ordinanceCitation Woodland MPFP Nexus Study 2019; Administrative Guidelines adopted 2019-07-02

Development Impact Fee - Police

Levied by City of Woodland on new development in Woodland. Collected at building permit.

What one house pays

$852

For a typical home: a 2,000 sq ft detached house on a 0.13 acre lot, on a new subdivision lot — this fee varies by zone and house size, so see the full schedule below.

Share of Woodland's total
2%
Total one-time fees here
$55,141
Adjustment
Adjusts yearly · another named index · January
what the document says

annual inflation adjustment per MPFP administrative guidelines

Next expected change
1 Jan 2027 rate on file is stale
!

A scheduled adjustment has passed since this rate took effect

This fee escalates annually. The rate on file is effective 1 Jan 2025, and at least one adjustment has fallen due since. The current amount is probably different, and for an indexed fee almost certainly higher. The next change after that is expected 1 Jan 2027.

The figure is published as held rather than projected forward, because a number computed from an index is not a number quoted from an adopted schedule. It is flagged so you can check the agency's current schedule before relying on it.

The record

Why it exists

“New development in the City will result in an increase in the service population and, therefore, in the demand for the services provided the City's Police Department. The purpose of the MPFP Police Fee is to provide funding for additional facilities, equipment, and vehicles that are needed to provide police services to the expanded service population.”

Nexus Study Update, April 2019, Ch. 5 "AB 1600 Nexus Finding", heading "Police — Purpose of Fee", report p. 60 · source document ↗
What it pays for

“The MPFP Police Fee will be used for facility improvements and the acquisition of equipment and vehicles needed to accommodate increased demand for police services as a result of new development. The improvements include construction of a new communications facility and a new animal shelter, the acquisition of police vehicles and equipment, and development of a new communications and records management system.”

Nexus Study Update, April 2019, Ch. 5, heading "Police — Use of Fee", report p. 60 · source document ↗
Where it applies

“The MPFP Fee Program applies to all development in the City. All new residential and nonresidential commercial development that occurs in the City shall pay the MPFP Fees in effect at the time that a building permit is issued.”

Nexus Study Update, April 2019, Ch. 6 "Implementation", "Introduction", report p. 64 · source document ↗
When it was adopted

“The Major Projects Financing Plan (MPFP) Fee Program was established in the 1990s to fund backbone infrastructure and other public facilities required to serve development in the City of Woodland (City). Since the MPFP Fee Program was established, the City has adopted several periodic updates to the MPFP Fee Program to reflect changes in land uses, facilities requirements and costs, funding sources, and the fee calculation methodology. The last MPFP Fee Nexus Study Update and comprehensive MPFP Fee Program update were adopted by the City in December 2008.”

Major Projects Financing Plan Fee Program Nexus Study Update, Final Report, EPS, April 2019, Ch. 1 "Background", report p. 1 · source document ↗
When it is paid

at building permit

“Development fees will be included in the cost of the building permit and are due prior to issuance of the building permit. In the case of connection to services without a building permit, fees will be paid prior to connection.”

City of Woodland, "DEVELOPMENT FEE PACKAGE / EFFECTIVE JANUARY 1, 2025", NOTES, item 2, p. 1 · source document ↗
Who collects it

City of Woodland, the agency that levies it

“The MPFP Fee Program development impact fees are collected at building permit issuance from developers of residential and commercial property. The City administers the MPFP Fee Program and collects the MPFP Fees.”

Nexus Study Update, April 2019, Ch. 1 "Background", report p. 1 · source document ↗
Who is exempt

“Contact Community Development Department for fees related to ADU's. No MPFP fees shall be charged on an ADU < 750 sq. ft.”

"DEVELOPMENT IMPACT FEES / Effective January 1, 2025", footnote block beneath Tables 1-4, p. 2 · source document ↗
Credits and offsets

“If adequate funding has been collected for a certain improvement, an approximate date must be specified as to when construction on the improvement will begin. If the findings show no need for the unspent funds or if the conditions discussed above are not met, and the administrative costs of the refund do not exceed the refund itself, the local agency that has collected the funds must refund them.”

Nexus Study Update, April 2019, Ch. 6 "Reviews and Accounting", "Surplus Funds", report p. 65 · source document ↗

Every published rate

Land useHouse sizeBasisEffectiveAmount
Greenfield
Single-family detached this home per DU 1 Jan 2025 $852.00

“Police $852 $852 $852”

"DEVELOPMENT IMPACT FEES / Effective January 1, 2025", Table 1, Residential / Single-Family, INFILL column, p. 2; column headings "Greenfield | Spring Lake | Infill", and note 5 on p. 1 reads "All Residential fees are calculated per unit" · source document ↗
Spring Lake
Single-family detached this home per DU 1 Jan 2025 $852.00

“Police $852 $852 $852”

"DEVELOPMENT IMPACT FEES / Effective January 1, 2025", Table 1, Residential / Single-Family, INFILL column, p. 2; column headings "Greenfield | Spring Lake | Infill", and note 5 on p. 1 reads "All Residential fees are calculated per unit" · source document ↗
Infill
Single-family detached this home per DU 1 Jan 2025 $852.00

“Police $852 $852 $852”

"DEVELOPMENT IMPACT FEES / Effective January 1, 2025", Table 1, Residential / Single-Family, INFILL column, p. 2; column headings "Greenfield | Spring Lake | Infill", and note 5 on p. 1 reads "All Residential fees are calculated per unit" · source document ↗
Greenfield; Spring Lake
Multi-family Multi-Family per DU — $638.00
the line this rate was read from

“Multi-Family / Greenfield Spring Lake Infill Corridor Downtown ... Police $638 $638 $610 $610 $610”

the levying document · source document ↗
Infill; Corridor; Downtown
Multi-family Multi-Family per DU — $610.00
the line this rate was read from

“Multi-Family / Greenfield Spring Lake Infill Corridor Downtown ... Police $638 $638 $610 $610 $610”

the levying document · source document ↗
Greenfield; Spring Lake; Infill; Corridor; Downtown
Multi-family Small Multi-Family (Less than 700 square feet) per DU — $425.00
the line this rate was read from

“Small Multi-Family (Less than 700 square feet) / Greenfield Spring Lake Infill Corridor Downtown ... Police $425 $425 $425 $425 $425”

the levying document · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close