The record
“A. REGIONAL ONE TIME SPECIAL TAXES (Regional OTSTs) — Regional OTSTs replace the payment of specific development impact fees currently required by the City's Book of Fees for Bridge District developments. … B. BRIDGE DISTRICT ONE TIME SPECIAL TAX (Bridge OTST) — The Bridge OTST will be used to fund the construction of Bridge District Authorized Facilities, including all Annual Cost Items such as debt service on the CFD bonds, as necessary.”
“Regional OTSTs replace the payment of specific development impact fees currently required by the City's Book of Fees for Bridge District developments. The following required impact fees are replaced by the corresponding Regional OTSTs: Water (debt service towards the water treatment plant); Sewer Collections; Police Facilities; Fire Facilities; Corporation Yard; City Hall Addition; Childcare Facilities. ... The Bridge OTST will be used to fund the construction of Bridge District Authorized Facilities, including all Annual Cost Items such as debt service on the CFD bonds, as necessary.”
“The Bridge District (formally called the Triangle Area) is a planned urban community located along the banks of the Sacramento River bounded by Tower Bridge to the north and Pioneer Bridge to the south.”
“The Bridge District Special Tax Program Fees were established on December 16, 2009 by City Council adoption of the Resolution of Intention to Establish Community Facilities District No. 27, prepared by Economic and Planning Systems, Inc.”
“The Bridge District Special Tax Program Fees were established on December 16, 2009 by City Council adoption of the Resolution of Intention to Establish Community Facilities District No. 27, prepared by Economic and Planning Systems, Inc.”
other: prior to final inspection - the City may withhold final inspection until the special taxes are paid in full.
“All OTSTs will be due and payable prior to final inspection. Final inspection may be delayed until OTSTs are paid in full.”
City of West Sacramento — Community Facilities District No. 27, the agency that levies it
“City of West Sacramento Engineering Division FEE SCHEDULE M BRIDGE DISTRICT SPECIAL TAXES”
“The Developer may request a Supplemental Special Tax Rate in order to reduce the amount of the Bridge OTST. Such request must be submitted to the Finance Department prior to the issuance of the engineering permit(s) for the project.”
“Tiered OTSTs: All OTSTs (Regional and Bridge) have been tiered to provide lower fee burdens to the earlier phases of development. All three tiers reflect reduced special taxes representing the application of urban standards to the Bridge District's proportionate allocation of costs for select facilities. The three development tiers are summarized below: • Tier 1: First 1 million building square feet • Tier 2: Between 1 million and 6 million building square feet • Tier 3: More than 6 million building square feet”
Every published rate
Every rate below applies to single-family detached.
| Applies to | Basis | Effective | Amount |
|---|---|---|---|
| Bridge District / Triangle | |||
| all uses - Tier 3 | per unit of Developed Land Area (basis unverified) | 1 Jan 2021 | $12.31 |
the line this rate was read from
Fee Schedule M (continued), January 1, 2021, printed page 35, "OTST RATES:" — Bridge OTST table, Tier 3 column. Full row as printed: "All uses $2.06 $10.26 $12.31". No unit is printed against the table. · source document ↗
| |||
| regional (residential) - Tier 2 | per unit of Developed Land Area (basis unverified) | 1 Jan 2021 | $11.03 |
the line this rate was read from
Fee Schedule M (continued), January 1, 2021, printed page 35, "OTST RATES:" — Regional OTST table, Residential column, Total row, Tier 3 column. Full row as printed: "Total $3.49 $11.03 $11.03". No unit is printed against the table. · source document ↗
| |||
| regional (residential) - Tier 3 | per unit of Developed Land Area (basis unverified) | 1 Jan 2021 | $11.03 |
the line this rate was read from
Fee Schedule M (continued), January 1, 2021, printed page 35, "OTST RATES:" — Regional OTST table, Residential column, Total row, Tier 3 column. Full row as printed: "Total $3.49 $11.03 $11.03". No unit is printed against the table. · source document ↗
| |||
| all uses - Tier 2 | per unit of Developed Land Area (basis unverified) | 1 Jan 2021 | $10.26 |
the line this rate was read from
Fee Schedule M (continued), January 1, 2021, printed page 35, "OTST RATES:" — Bridge OTST table, Tier 2 column. Full row as printed: "All uses $2.06 $10.26 $12.31". No unit is printed against the table. · source document ↗
| |||
| regional (residential) - Tier 1 | per unit of Developed Land Area (basis unverified) | 1 Jan 2021 | $3.49 |
the line this rate was read from
Fee Schedule M (continued), January 1, 2021, printed page 35, "OTST RATES:" — Regional OTST table, Residential column, Total row, Tier 1 column. Full row as printed: "Total $3.49 $11.03 $11.03". No unit is printed against the table. · source document ↗
| |||
| all uses - Tier 1 | per unit of Developed Land Area (basis unverified) | 1 Jan 2021 | $2.06 |
the line this rate was read from
Fee Schedule M (continued), January 1, 2021, printed page 35, "OTST RATES:" — Bridge OTST table, Tier 1 column. Full row as printed: "All uses $2.06 $10.26 $12.31". No unit is printed against the table. · source document ↗
| |||