DevFeeFinder
Sewer - treatmentSet by connection chargeCitation Visalia Resolution No. 2026-02 (amounts carried from Res. 2019-06)

Treatment Plant Connection Capacity Charge

Levied by City of Visalia on new development in Visalia. Collected other: upon connection to the City sanitary sewer system (VMC 13.08.770 is identified as the section governing the timing of payment of the treatment facility connection charge; that section's text was not reachable).

What one house pays

$1,026

For a typical home: a 2,000 sq ft detached house on a 0.13 acre lot, on a new subdivision lot.

Share of Visalia's total
3%
Total one-time fees here
$37,610
Adjustment
Adjusts only when the board sets a new amount
what the document says

by resolution - reviewed annually, unchanged since 2019

Next expected change
1 Jul 2027

The record

Why it exists

“WHEREAS, VMC section 13.08.750, et seq., authorizes the imposition of treatment plant connection charges by resolution for connection to the sanitary sewer system and provides that review and amendment of such fees may be initiated by the Council from time to time as necessary to meet increasing costs or changed conditions of providing trunk sewer or oversize service and adjusted by resolution; and”

Attachment A, Resolution No. 2026-02, adopted 2026-06-15, recitals · source document ↗
What it pays for

“The City of Visalia has established an impact fee schedule that is applied to all residential, commercial and industrial developments. These one-time fees are intended to pay for the capital cost associated with the infrastructure needs of the development project. Impact fees pay for such items as park acquisition, public safety facilities, storm drainage basins, street improvements and sanitary sewer infrastructure. As they relate to the treatment plant and sewer mains, impact fees reflect the portion of capacity utilized by the industry that is no longer available for use by others.”

City of Visalia Agenda Item Transmittal, meeting date 10/15/2012, "Background Discussion" · source document ↗
Where it applies

“As part of that role the City owns and operates the wastewater collection and treatment system within the City and has passed municipal code ordinances concerning the operation of the sewer system”

Ordinance 2012-13, Section 1 · source document ↗
Who adopted it

Resolution No. 2019-06 (the resolution the amounts are footed to; original adoption of the charge not established)

“CONNECTION FEES / TREATMENT PLANT CONNECTION CAPACITY CHARGES ... RESIDENTIAL / Single family, Apartment, Mobile Home Park Per Unit $ 1,026.00 ... Resolution No. 2019-06”

City of Visalia Rates & Fees FY 2025-26, p. 41, table footer · source document ↗
When it is paid

“The City of Visalia owns and operates the sanitary sewer collection and treatment system within the City. All residential, commercial and industrial users of this system are required to pay one-time impact fees upon connection. This fee is set by the City Council and is reviewed annually.”

City of Visalia Agenda Item Transmittal, 10/15/2012, "Summary" · source document ↗
Who collects it

City of Visalia, the agency that levies it

“Section 3: Section 13.08.770 of the Visalia Municipal Code, which outlines the timing of payment of the treatment facility connection charge, is hereby amended to add Section 13.08.770 (E) as follows:”

Ordinance 2012-13, Section 3 · source document ↗
How it changes

“Unless otherwise indicated in the Rates & Fees document (attached hereto as Attachment "A"), these rates and fees go into effect on July 1, 2026. Impact fees shall not be effective until 60 days after the adoption thereof (August 14, 2026).”

Attachment A, Resolution No. 2026-02, adopted 2026-06-15, resolved clause · source document ↗

Every published rate

Every rate below applies to single-family detached.

RateBasisEffectiveAmount
this home per DU 14 Aug 2026 $1,026

“RESIDENTIAL (Single family, Apartment, Mobile Home Park) $ 1,026.00 /unit”

City of Visalia Development Fee Schedule FY 2026-27, printed p. 17, table "CONNECTION FEES / TREATMENT PLANT CONNECTION CAPACITY CHARGES", header "RESOLUTION NO. 2026-02 — Effective August 14, 2026" · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close