Public safetySet by county fee ordinanceCitation Solano County Code ch. 11 Art. X; Resolution No. 2019-156, adopted 2019-08-06, effective 2019-10-06

Solano County Public Facilities Fee

Levied by County of Solano (Board of Supervisors) on new development in Vacaville. Collected at certificate of occupancy or final inspection, whichever is first; at building permit issuance where Gov. Code s. 66007 is met.

What one house pays

$9,263

For a typical home: a 2,000 sq ft detached house on a 0.13 acre lot, on a new subdivision lot — this fee varies by house size, so see the full schedule below.

Share of Vacaville's total
12%
Total one-time fees here
$76,152
Adjustment
Adjusts yearly · ENR construction cost index
what the document says

ENR Construction Cost Index or similar, at most annually, by resolution of the Board of Supervisors (permissive; none adopted since 2019)

Next expected change
1 Jul 2027 rate on file is stale
!

A scheduled adjustment has passed since this rate took effect

This fee escalates annually. The rate on file is effective 6 Oct 2019, and at least one adjustment has fallen due since. The current amount is probably different, and for an indexed fee almost certainly higher. The next change after that is expected 1 Jul 2027.

The figure is published as held rather than projected forward, because a number computed from an index is not a number quoted from an adopted schedule. It is flagged so you can check the agency's current schedule before relying on it.

The record

Where it applies

“Whereas, pursuant to Article X of Chapter 11 of the Solano County Code, public facilities fees are imposed on all new nonexempt construction in the County of Solano, including the incorporated areas of the County”

Resolution No. 2019-156, adopted 2019-08-06, first Whereas · source document ↗
When it is paid

“The city will collect a fee for all non-exempt property pursuant to provisions of this ordinance, or as that fee may be modified from time to time, at the time of the issuance of a certificate of occupancy or upon final inspection, whichever occurs first, or if the provisions of Government Code section 66007 are met, at the time of issuance of a building permit.”

Solano County Code ch. 11 Art. X, s. 11-134(a) · source document ↗
Who collects it

City of Vacaville, under a separate agreement with the County, remitting quarterly

“Each incorporated city within the County shall, pursuant to a separate agreement entered into between that city and the County, collect the fee required under the provisions of this ordinance, and in the amount as may be amended by subsequent County resolution, on behalf of the County.”

Solano County Code ch. 11 Art. X, s. 11-134(a) City collection of fees · source document ↗
Credits and offsets

reduced by any fee another jurisdiction charges the developer for the same County facilities

“The amount payable shall be reduced by the amount of any fee charged to the developer by any other jurisdiction to provide funding for the same County facilities.”

Solano County Code ch. 11 Art. X, s. 11-133(b) · source document ↗

Every published rate

Land useHouse sizeBasisEffectiveAmount
Single-family detached this home per DU 6 Oct 2019 $9,263

“Solano County Current Public Facilities Fee Summary / Incorporated and Unincorporated Areas of Solano County / Residential, Fee Amount per Unit ... Single Family Residential (SFR) Unit | 1,658.86 | 2,302.12 | 1,672.43 | 1,030.38 | 30.00 | 68.95 | 6,762.74 | 2,500.00 | $ 9,263”

Solano County Current Public Facilities Fee Summary, Attachment B to Board File 25-1017 (annual disclosure accepted 2025-12-09), table "Incorporated and Unincorporated Areas of Solano County" · source document ↗
Multi-family none per DU 6 Oct 2019 $6,662
the line this rate was read from

“Solano County Current Public Facilities Fee Summary / Incorporated and Unincorporated Areas of Solano County / Residential, Fee Amount per Unit ... Multi-Family Residential (MFR) Unit | 1,293.25 | 1,794.74 | 1,303.84 | 803.30 | 16.80 | 49.59 | 5,261.52 | 1,400.00 | $ 6,662”

Solano County Current Public Facilities Fee Summary, Attachment B to Board File 25-1017 (annual disclosure accepted 2025-12-09), table "Incorporated and Unincorporated Areas of Solano County" · source document ↗
ADU 750 sq ft or more (waived under 750 sq ft; prorated to a maximum of $4,536) per DU 6 Oct 2019 $4,536
the line this rate was read from

“Solano County Current Public Facilities Fee Summary / Incorporated and Unincorporated Areas of Solano County / Residential, Fee Amount per Unit ... 2nd SFR Unit / Accessory Dwelling Unit (ADU)** | 818.53 | 1,135.91 | 825.21 | 508.43 | 14.40 | 33.77 | 3,336.25 | 1,200.00 | $ 4,536”

Solano County Current Public Facilities Fee Summary, Attachment B to Board File 25-1017 (annual disclosure accepted 2025-12-09), table "Incorporated and Unincorporated Areas of Solano County" · source document ↗
Senior none per DU 6 Oct 2019 $3,975
the line this rate was read from

“Solano County Current Public Facilities Fee Summary / Incorporated and Unincorporated Areas of Solano County / Residential, Fee Amount per Unit ... Age-Restricted / Senior Multi-family | 818.53 | 1,135.91 | 825.21 | 508.43 | 7.80 | 29.59 | 3,325.47 | 650.00 | $ 3,975”

Solano County Current Public Facilities Fee Summary, Attachment B to Board File 25-1017 (annual disclosure accepted 2025-12-09), table "Incorporated and Unincorporated Areas of Solano County" · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close