DevFeeFinder
ParksSet by county fee ordinanceCitation County PLDO, Ord. No. 10554 (N.S.), adopted 7/25/2018, effective 1/1/2019

Park Land Dedication Ordinance (PLDO) fees - Mountain Empire

Levied by San Diego County Parks & Recreation on new development in San Diego County (unincorporated). Collected at building permit.

What one house pays

$8,845

This fee is not in San Diego County (unincorporated)'s published figure. This site publishes a home outside any plan area, and this charge applies only in Mountain Empire. The amount shown is what it costs a house that is there.

Total one-time fees here
$68,467
Adjustment
Not recorded

The record

Why it exists

“SEC. 810.109. PARK IMPACT FEES PURPOSE — The ordinance section codified in this article is enacted pursuant to the authority granted by California Government Code Sections 66000 et seq (also known as the Mitigation Fee Act), which authorizes a county to require the payment of an impact fee to defray all or a portion of the cost of public facilities needed to accommodate the new residents of a development project as a condition of project approval. (a) Park Land Acquisition Impact Fees collected pursuant to this Article are intended to fund the acquisition of park land which will mitigate impacts of new residential Developments without Subdivisions on park land within the unincorporated County ... (b) Park Improvement Impact Fees collected pursuant to this Article are intended to fund park improvements which will mitigate the impacts of new residential Developments with or without Subdivisions on parks and recreational facilities within the unincorporated County”

Ordinance No. 10554 (N.S.), 2018-07-25, Art. 3, s. 810.109, p. 8 · source document ↗
What it pays for

“USE OF PARK IMPACT FEES — The Park Impact Fee consists of an administrative fee, park land acquisition fee and park improvement fee. Administrative fees fund annual reporting requirements and administration of LPPA funds. Park Land Acquisition Impact Fees fund the acquisition of park land. Park Improvement Impact Fees fund the development of new or expansion of existing park or recreation facilities. Please see Section 810.115 Limitations on Use for more details on the use of Park Impact Fees.”

County of San Diego Dept. of Parks and Recreation, "Park Land Dedication Ordinance (PLDO)", section "USE OF PARK IMPACT FEES"; archived copy sources/99/994995d5d60d11b3d0abba83e8bf9202b473588d180d7a77ecf5de02f763b63e.html · source document ↗
When it was adopted

2018-07-25 (original PLDO 1972-12-19; this chapter effective 2019-01-01)

“ORDINANCE NO.: 10554 (N.S.) — AN ORDINANCE REPEALING AND REPLACING THE SAN DIEGO COUNTY CODE OF REGULATORY ORDINANCES TITLE 8, DIVISION 10, CHAPTER 1, RELATING TO PARK LAND DEDICATION AND PAYMENT OF FEES ... SECTION 1. Chapter 1 of Division 10 of Title 8 of the San Diego County Code of Regulatory Ordinances is hereby repealed and replaced with the following: ... PASSED, APPROVED, AND ADOPTED by the Board of Supervisors of the County of San Diego this 25th day of July, 2018. ... AYES: Cox, Gaspar, Roberts, Horn ABSENT: Jacob”

Ordinance No. 10554 (N.S.), meeting date 07/25/18 (4), title page / Section 1 / signature page, pp. 1 and 15 · source document ↗
Who adopted it

Ordinance No. 10554 (N.S.)

“ORDINANCE NO.: 10554 (N.S.) — AN ORDINANCE REPEALING AND REPLACING THE SAN DIEGO COUNTY CODE OF REGULATORY ORDINANCES TITLE 8, DIVISION 10, CHAPTER 1, RELATING TO PARK LAND DEDICATION AND PAYMENT OF FEES ... SECTION 1. Chapter 1 of Division 10 of Title 8 of the San Diego County Code of Regulatory Ordinances is hereby repealed and replaced with the following: ... PASSED, APPROVED, AND ADOPTED by the Board of Supervisors of the County of San Diego this 25th day of July, 2018. ... AYES: Cox, Gaspar, Roberts, Horn ABSENT: Jacob”

Ordinance No. 10554 (N.S.), meeting date 07/25/18 (4), title page / Section 1 / signature page, pp. 1 and 15 · source document ↗
When it is paid

at building permit

“(c) The payment of Park Impact Fees shall be required prior to issuance of any building permit or other permit required for construction of a dwelling unit, where Park Impact Fees have been established by the Board of Supervisors resolution or ordinance. Park Impact Fees shall be determined in accordance with the fee schedule approved by the applicable Board of Supervisors resolution in effect at the time fees are paid, and may include an automatic increase.”

Ordinance No. 10554 (N.S.), 2018-07-25, s. 810.111(c), p. 10 · source document ↗
Who is exempt

“SEC. 810.112. PARK IMPACT FEE EXEMPTIONS — The following uses shall be exempt from both the Park Land Acquisition Impact Fee and the Park Improvement Impact Fee, unless otherwise stated: (a) Any residential Development that involves the Subdivision of land and pays the Park In-Lieu Fee is exempt from the Park Land Acquisition Impact Fee. (b) Any Development that does not require a County building permit. (c) Any nonresidential Development. (d) The replacement on the same parcel by the owner of a dwelling or dwellings destroyed by fire, flood, earthquake, or other calamity, provided that the application for a building permit to replace such dwelling is filed with the Director within two (2) years after destruction of the dwelling and is filed by the homeowner impacted by the calamity. (e) Rehabilitation, replacement, or reconstruction of residential structures that were lawfully constructed. ... (i) Any farm employee housing or farm labor camp project.”

Ordinance No. 10554 (N.S.), 2018-07-25, s. 810.112, pp. 10-11 · source document ↗
Credits and offsets

“SEC. 810.113. CREDIT FOR PARK LAND ACQUISITION IMPACT FEE. (a) In the event that an applicant subject to the Park Land Acquisition Impact Fee seeks to dedicate land for parks, the Approving Body may allow a credit for up to 100% of the Park Land Acquisition Impact Fee payment required by this Chapter, if the land dedication amount is greater than 0.4 contiguous acres. For land dedication amounts less than 0.4 contiguous acres, only fees will be accepted, unless otherwise approved by the Director or Approving Body.”

Ordinance No. 10554 (N.S.), 2018-07-25, s. 810.113(a), p. 11 · source document ↗

Every published rate

Every rate below applies to single-family detached.

RateBasisEffectiveAmount
Mountain Empire
per DU 1 Jan 2026 $8,845
the line this rate was read from

“2026 SINGLE-FAMILY DWELLING UNIT PLDO PARK IMPACT FEES | LOCAL PARK PLANNING AREA | LAND ACQUISITION IMPACT FEE* | PARK IN-LIEU IMPACT FEE** | PARK IMPROVEMENT IMPACT FEE | ADMINISTRATION FEE | TOTAL PARK IMPACT FEE — Mountain Empire | $108 | $108 | $8,564 | $173 | $8,845 — *Non-Subdivision Residential Project **Subdivision Residential Project”

County of San Diego Dept. of Parks and Recreation, "Park Land Dedication Ordinance (PLDO)", 2026 SINGLE-FAMILY DWELLING UNIT PLDO PARK IMPACT FEES, anchor #Single · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close