ParksSet by county fee ordinanceCitation County PLDO, Ord. No. 10554 (N.S.), adopted 7/25/2018, effective 1/1/2019

Park Land Dedication Ordinance (PLDO) fees - County Islands

Levied by County of San Diego, Department of Parks and Recreation (DPR) on new development in San Diego County (unincorporated). Collected at building permit.

What one house pays

$13,781

For a typical home: a 2,000 sq ft detached house on a 0.13 acre lot, on a new subdivision lot.

Share of San Diego County (unincorporated)'s total
20%
Total one-time fees here
$68,467
Adjustment
Adjusts yearly · ENR construction cost index · January
what the document says

annual, automatic, effective each January 1 — Park Impact Fees on the one-year change (October to October) in the Engineering News Record Los Angeles Construction Cost Index; Park Land Acquisition Impact Fee and Park In-Lieu Fee on 40% of the one-year change in median sale price in Sandicor's San Diego Cost Index

Next expected change
1 Jan 2027

The record

Why it exists

“SEC. 810.109. PARK IMPACT FEES PURPOSE — The ordinance section codified in this article is enacted pursuant to the authority granted by California Government Code Sections 66000 et seq (also known as the Mitigation Fee Act), which authorizes a county to require the payment of an impact fee to defray all or a portion of the cost of public facilities needed to accommodate the new residents of a development project as a condition of project approval.”

Ord. 10554 (N.S.), 07/25/2018, Art. 3, SEC. 810.109, p.8 · source document ↗
What it pays for

“SEC. 810.115. LIMITATIONS ON USE. (a) The Park In-Lieu Fee paid pursuant to this Chapter shall only be used for the purpose of acquiring park land, developing new, or rehabilitating existing park or recreation facilities. (b) The Park Land Acquisition Fee paid pursuant to Section 810.1124(a) and (b) shall only be used for the purpose of acquiring new parkland. (c) The Park Improvement Impact Fee paid pursuant to Chapter shall only be used for the purpose of developing new, or expansion of existing park or recreation facilities. (d) Park Impact Fees and Park In-Lieu Fees shall not be used to provide recreational services, programming or operations and maintenance of parks and recreational facilities.”

Ord. 10554 (N.S.), 07/25/2018, Art. 4, SEC. 810.115, pp.12-13 · source document ↗
Where it applies

“(e) "Local Park Planning Area" means the geographical area(s) depicted on the Local Park Planning Area map on file with the Department of Parks and Recreation. Local Park Impact Areas coincide with the Community and Subregional Planning Area boundaries in Figure I-2 of the County of San Diego General Plan and as depicted on the Local Park Planning Area Map on file with the Department of Parks and Recreation.”

Ord. 10554 (N.S.), 07/25/2018, Art. 1, SEC. 810.101(e), p.1 · source document ↗
When it was adopted

2018-07-25 (adopted); effective 2019-01-01

“ORDINANCE NO.: 10554 (N.S.) / AN ORDINANCE REPEALING AND REPLACING THE SAN DIEGO COUNTY CODE OF REGULATORY ORDINANCES TITLE 8, DIVISION 10, CHAPTER 1, RELATING TO PARK LAND DEDICATION AND PAYMENT OF FEES ... PASSED, APPROVED, AND ADOPTED by the Board of Supervisors of the County of San Diego this 25th day of July, 2018.”

Ordinance No. 10554 (N.S.), Meeting Date: 07/25/18 (4), title page p.1 and signature page p.15 · source document ↗
Who adopted it

Ordinance No.: 10554 (N.S.)

“ORDINANCE NO.: 10554 (N.S.) / AN ORDINANCE REPEALING AND REPLACING THE SAN DIEGO COUNTY CODE OF REGULATORY ORDINANCES TITLE 8, DIVISION 10, CHAPTER 1, RELATING TO PARK LAND DEDICATION AND PAYMENT OF FEES ... PASSED, APPROVED, AND ADOPTED by the Board of Supervisors of the County of San Diego this 25th day of July, 2018.”

Ordinance No. 10554 (N.S.), Meeting Date: 07/25/18 (4), title page p.1 and signature page p.15 · source document ↗
When it is paid

at building permit

“(c) The payment of Park Impact Fees shall be required prior to issuance of any building permit or other permit required for construction of a dwelling unit, where Park Impact Fees have been established by the Board of Supervisors resolution or ordinance. Park Impact Fees shall be determined in accordance with the fee schedule approved by the applicable Board of Supervisors resolution in effect at the time fees are paid, and may include an automatic increase.”

Ord. 10554 (N.S.), 07/25/2018, Art. 3, SEC. 810.111(c), p.10 · source document ↗
Who collects it

County of San Diego, Planning & Development Services (PDS)

“PLDO park impact fees are paid at issuance of a ministerial building permit for a dwelling unless previously paid or exempted by the PLDO. Please note that park impact fees for permits issued only in the unincorporated areas are collected by the PDS on behalf of the DPR.”

"Park Land Dedication Ordinance (PLDO)", section "PLDO - Private Residential Development Projects", under heading "PARK IMPACT FEES AND PARK LAND DEDICATION REQUIREMENTS" · source document ↗
Who is exempt

“SEC. 810.112. PARK IMPACT FEE EXEMPTIONS — The following uses shall be exempt from both the Park Land Acquisition Impact Fee and the Park Improvement Impact Fee, unless otherwise stated: (a) Any residential Development that involves the Subdivision of land and pays the Park In-Lieu Fee is exempt from the Park Land Acquisition Impact Fee. (b) Any Development that does not require a County building permit. (c) Any nonresidential Development. (d) The replacement on the same parcel by the owner of a dwelling or dwellings destroyed by fire, flood, earthquake, or other calamity, provided that the application for a building permit to replace such dwelling is filed with the Director within two (2) years after destruction of the dwelling and is filed by the homeowner impacted by the calamity. (e) Rehabilitation, replacement, or reconstruction of residential structures that were lawfully constructed. ... (g) Recreational Trailer Parks, Temporary Trailer Parks, or Travel Trailer Parks, as those terms are defined in the Mobilehome Parks Act. ... (i) Any farm employee housing or farm labor camp project.”

Ord. 10554 (N.S.), 07/25/2018, Art. 3, SEC. 810.112, pp.10-11 · source document ↗
Credits and offsets

“SEC. 810.113. CREDIT FOR PARK LAND ACQUISITION IMPACT FEE. (a) In the event that an applicant subject to the Park Land Acquisition Impact Fee seeks to dedicate land for parks, the Approving Body may allow a credit for up to 100% of the Park Land Acquisition Impact Fee payment required by this Chapter, if the land dedication amount is greater than 0.4 contiguous acres. For land dedication amounts less than 0.4 contiguous acres, only fees will be accepted, unless otherwise approved by the Director or Approving Body.”

Ord. 10554 (N.S.), 07/25/2018, Art. 3, SEC. 810.113(a), p.11 · source document ↗

Every published rate

Land useApplies toBasisEffectiveAmount
County Islands
Multi-family per DU 1 Jan 2026 $14,929
the line this rate was read from

“2026 MULTI-FAMILY DWELLING UNIT PLDO PARK IMPACT FEES | LOCAL PARK PLANNING AREA | LAND ACQUISITION IMPACT FEE* | PARK IN-LIEU IMPACT FEE** | PARK IMPROVEMENT IMPACT FEE | ADMINISTRATION FEE | TOTAL PARK IMPACT FEE — County Islands | $2,236 | $2,236 | $12,400 | $293 | $14,929 — *Non-Subdivision Residential Project **Subdivision Residential Project”

County of San Diego Dept. of Parks and Recreation, "Park Land Dedication Ordinance (PLDO)", 2026 MULTI-FAMILY DWELLING UNIT PLDO PARK IMPACT FEES, anchor #Multi · source document ↗
Single-family detached this home per DU 1 Jan 2026 $13,781

“2026 SINGLE-FAMILY DWELLING UNIT PLDO PARK IMPACT FEES | LOCAL PARK PLANNING AREA | LAND ACQUISITION IMPACT FEE* | PARK IN-LIEU IMPACT FEE** | PARK IMPROVEMENT IMPACT FEE | ADMINISTRATION FEE | TOTAL PARK IMPACT FEE — County Islands | $2,032 | $2,032 | $11,478 | $270 | $13,781 — *Non-Subdivision Residential Project **Subdivision Residential Project”

County of San Diego Dept. of Parks and Recreation, "Park Land Dedication Ordinance (PLDO)", 2026 SINGLE-FAMILY DWELLING UNIT PLDO PARK IMPACT FEES, anchor #Single · source document ↗
ADU none per DU — $5,338
the line this rate was read from

“2026 ACCESSORY DWELLING UNIT PLDO PARK IMPACT FEES | LOCAL PARK PLANNING AREA | LAND ACQUISITION IMPACT FEE* | PARK IN-LIEU IMPACT FEE** | PARK IMPROVEMENT IMPACT FEE | ADMINISTRATION FEE | TOTAL PARK IMPACT FEE — County Islands | $773 | $773 | $4,461 | $105 | $5,338 — *Non-Subdivision Residential Project **Subdivision Residential Project”

County of San Diego Dept. of Parks and Recreation, "Park Land Dedication Ordinance (PLDO)", 2026 ACCESSORY DWELLING UNIT PLDO PARK IMPACT FEES, anchor #Accessory · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.