TransportationSet by city fee ordinanceCitation SPRTA Resolution #26-02, adopted 2026-03-25, effective 2026-07-01

SPRTA Regional Transportation and Air Quality Mitigation Fee (Tier 1)

Levied by South Placer Regional Transportation Authority (SPRTA), a joint powers authority of the Cities of Lincoln, Rocklin, Roseville and the County of Placer, staffed by the Placer County Transportation Planning Agency on new development in Roseville. Authorized under the Mitigation Fee Act - Gov. Code Sec. 66000 et seq. Collected prior to building permit issuance.

What one house pays

$2,036

For a typical home: a 2,000 sq ft detached house on a 0.13 acre lot, on a new subdivision lot — this fee varies by zone and house size, so see the full schedule below.

Share of Roseville's total
2%
Total one-time fees here
$82,135
Adjustment
Adjusts yearly · ENR construction cost index
what the document says

annual, average of the ENR Construction Cost Index "20 Cities" and "San Francisco" series, March to March

Next expected change
1 Jul 2027

The record

Why it exists

“WHEREAS, the Board of Directors of the Authority finds as follows: (i) The purpose of the Fee is to finance the public facilities (the "Facilities") described and identified in the Regional Transportation and Air Quality Mitigation Fee Improvement Program to reduce the impacts of increased traffic caused by New Development within the area of jurisdiction of the Authority;”

Resolution #26-02 of the Board of Directors, 25 March 2026, recitals, packet p. 8 · source document ↗
What it pays for

“(ii) The Fee shall be used to finance the Facilities (including, without limitation, planning, design, administration, environmental compliance, and construction costs of the Facilities);”

Resolution #26-02, 25 March 2026, recitals, packet p. 9 · source document ↗
Where it applies

“South Placer Regional Transportation (SPRTA) Tier II Fee: Assessed on all applications for new construction in the program area, which includes the City of Roseville, the City of Rocklin, the City of Lincoln and portions of Unincorporated Placer County, and collected prior to permit issuance.”

City of Roseville, "Residential Development Fees, July 2026 — June 2027", Updated July 1, 2026, Development Fees & Estimate Worksheet, booklet p. 13 · source document ↗
When it was adopted

2002-04 (fee effective 2002-07-01)

“In April 2002, the SPRTA Board adopted the Regional Transportation and Air Quality Mitigation Fee (commonly known as the Tier 1 Fee Program), which assessed new development for its impacts on specified regional transportation facilities. These fees went into effect on July 1, 2002.”

SPRTA Board memo, agenda item H, 2026-03-25, "Background", p. 3 · source document ↗
When it is paid

prior to building permit issuance

“South Placer Regional Transportation (SPRTA) Fee: Assessed on all applications for new construction in the program area, which includes the City of Roseville, the City of Rocklin, the City of Lincoln and portions of Unincorporated Placer County, and collected prior to permit issuance.”

City of Roseville, "Residential Development Fees July 2026 - June 2027", p. 13 · source document ↗
Who collects it

City of Roseville, Development Services Department

“The South Placer Regional Transportation Authority (SPRTA), formed in January 2002, is the result of those efforts. SPRTA is a joint powers authority comprised of the Cities of Lincoln, Rocklin, Roseville, and the County of Placer. The Authority is governed by a Board of Directors representing the JPA member jurisdictions and is staffed by the Placer County Transportation Planning Agency. The Board meets monthly or as needed.”

GHD, "Nexus Study Update Report — South Placer Regional Transportation Authority", October 2023, s. 1.2 "Background on the SPRTA Program", report p. 1 · source document ↗
Who is exempt

State and federal projects, ADUs under 750 sq ft, and K-12 schools

“Not all development that occurs in the SPRTA districts pays a SPRTA impact fee. State and Federal development projects are exempt from local fees as a matter of law, as are accessory dwelling units with a floor area of less than 750 square feet. Public kindergarten through grade 12 schools are also exempt from the fee as a matter of SPRTA policy.”

GHD, "Nexus Study Update Report, South Placer Regional Transportation Authority", January 2024, s. 1.2, p. 1 · source document ↗
Credits and offsets

“Certain specific plan areas have built improvements identified in the fee program and will receive a credit for these improvements. In addition, certain improvements identified in the Regional Fee program are also included within the City's Traffic Mitigation Fee program. In acknowledgement of this, the benefit districts within the City will receive a credit towards the Regional Fee and are reflected in the fee schedule.”

Residential Development Fees July 2026—June 2027, booklet p. 13, SPRTA Fee and SPRTA Tier II Fee entries · source document ↗
How it changes

“Effective Date. This Resolution and the Fee hereby approved shall be effective July 1, 2026, and complies with the 60-day waiting period following the action of this governing board, as required by AB 602.”

Resolution #26-02, 25 March 2026, "Effective Date", packet p. 9 · source document ↗

Every published rate

Every rate below applies to single-family detached.

House sizeBasisEffectiveAmount
Roseville West
>3,500 sq ft (Very Large) per DUE 1 Jul 2026 $2,321
the line this rate was read from

“210 | Single Family | Dwelling Unit | 0.83 | 1.00 | 1.08 | 1.14 | $1,690 | $2,036 | $2,199 | $2,321 — under "District: Roseville West", with the band headings "DUEs for Small (<1,500 sq.ft) | DUEs for Medium (1,500-2,500 sq.ft) | DUEs for Large (>2,500-3,500 sq.ft) | DUEs for Very Large (>3,500 sq.ft)"; this row is the >3,500 sq ft (Very Large) column”

SPRTA, "SPRTA Impact Fees" Tier 1 fee schedule, updated 2026-03-09, effective 2026-07-01, p. 9 (Roseville West) / p. 10 (Roseville East) · source document ↗
Large (>2,500-3,500 sq ft) per DUE 1 Jul 2026 $2,199
the line this rate was read from

“210 | Single Family | Dwelling Unit | 0.83 | 1.00 | 1.08 | 1.14 | $1,690 | $2,036 | $2,199 | $2,321 — under "District: Roseville West", with the band headings "DUEs for Small (<1,500 sq.ft) | DUEs for Medium (1,500-2,500 sq.ft) | DUEs for Large (>2,500-3,500 sq.ft) | DUEs for Very Large (>3,500 sq.ft)"; this row is the Large (>2,500-3,500 sq ft) column”

SPRTA, "SPRTA Impact Fees" Tier 1 fee schedule, updated 2026-03-09, effective 2026-07-01, p. 9 (Roseville West) / p. 10 (Roseville East) · source document ↗
Medium (1,500-2,500 sq ft)this home per DUE 1 Jul 2026 $2,036

“210 | Single Family | Dwelling Unit | 0.83 | 1.00 | 1.08 | 1.14 | $1,690 | $2,036 | $2,199 | $2,321 — under "District: Roseville West", with the band headings "DUEs for Small (<1,500 sq.ft) | DUEs for Medium (1,500-2,500 sq.ft) | DUEs for Large (>2,500-3,500 sq.ft) | DUEs for Very Large (>3,500 sq.ft)"; this row is the Medium (1,500-2,500 sq ft) column”

SPRTA, "SPRTA Impact Fees" Tier 1 fee schedule, updated 2026-03-09, effective 2026-07-01, p. 9 (Roseville West) / p. 10 (Roseville East) · source document ↗
Small (<1,500 sq ft) per DUE 1 Jul 2026 $1,690
the line this rate was read from

“210 | Single Family | Dwelling Unit | 0.83 | 1.00 | 1.08 | 1.14 | $1,690 | $2,036 | $2,199 | $2,321 — under "District: Roseville West", with the band headings "DUEs for Small (<1,500 sq.ft) | DUEs for Medium (1,500-2,500 sq.ft) | DUEs for Large (>2,500-3,500 sq.ft) | DUEs for Very Large (>3,500 sq.ft)"; this row is the Small (<1,500 sq ft) column”

SPRTA, "SPRTA Impact Fees" Tier 1 fee schedule, updated 2026-03-09, effective 2026-07-01, p. 9 (Roseville West) / p. 10 (Roseville East) · source document ↗
Roseville East
>3,500 sq ft (Very Large) per DUE 1 Jul 2026 $1,094
the line this rate was read from

“210 | Single Family | Dwelling Unit | 0.83 | 1.00 | 1.08 | 1.14 | $1,690 | $2,036 | $2,199 | $2,321 — under "District: Roseville East", with the band headings "DUEs for Small (<1,500 sq.ft) | DUEs for Medium (1,500-2,500 sq.ft) | DUEs for Large (>2,500-3,500 sq.ft) | DUEs for Very Large (>3,500 sq.ft)"; this row is the >3,500 sq ft (Very Large) column”

SPRTA, "SPRTA Impact Fees" Tier 1 fee schedule, updated 2026-03-09, effective 2026-07-01, p. 9 (Roseville West) / p. 10 (Roseville East) · source document ↗
Large (>2,500-3,500 sq ft) per DUE 1 Jul 2026 $1,037
the line this rate was read from

“210 | Single Family | Dwelling Unit | 0.83 | 1.00 | 1.08 | 1.14 | $1,690 | $2,036 | $2,199 | $2,321 — under "District: Roseville East", with the band headings "DUEs for Small (<1,500 sq.ft) | DUEs for Medium (1,500-2,500 sq.ft) | DUEs for Large (>2,500-3,500 sq.ft) | DUEs for Very Large (>3,500 sq.ft)"; this row is the Large (>2,500-3,500 sq ft) column”

SPRTA, "SPRTA Impact Fees" Tier 1 fee schedule, updated 2026-03-09, effective 2026-07-01, p. 9 (Roseville West) / p. 10 (Roseville East) · source document ↗
Medium (1,500-2,500 sq ft) per DUE 1 Jul 2026 $960.00
the line this rate was read from

“210 | Single Family | Dwelling Unit | 0.83 | 1.00 | 1.08 | 1.14 | $1,690 | $2,036 | $2,199 | $2,321 — under "District: Roseville East", with the band headings "DUEs for Small (<1,500 sq.ft) | DUEs for Medium (1,500-2,500 sq.ft) | DUEs for Large (>2,500-3,500 sq.ft) | DUEs for Very Large (>3,500 sq.ft)"; this row is the Medium (1,500-2,500 sq ft) column”

SPRTA, "SPRTA Impact Fees" Tier 1 fee schedule, updated 2026-03-09, effective 2026-07-01, p. 9 (Roseville West) / p. 10 (Roseville East) · source document ↗
Small (<1,500 sq ft) per DUE 1 Jul 2026 $797.00
the line this rate was read from

“210 | Single Family | Dwelling Unit | 0.83 | 1.00 | 1.08 | 1.14 | $1,690 | $2,036 | $2,199 | $2,321 — under "District: Roseville East", with the band headings "DUEs for Small (<1,500 sq.ft) | DUEs for Medium (1,500-2,500 sq.ft) | DUEs for Large (>2,500-3,500 sq.ft) | DUEs for Very Large (>3,500 sq.ft)"; this row is the Small (<1,500 sq ft) column”

SPRTA, "SPRTA Impact Fees" Tier 1 fee schedule, updated 2026-03-09, effective 2026-07-01, p. 9 (Roseville West) / p. 10 (Roseville East) · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close