Levied by City of Roseville — Roseville Electric Utility (municipal electric utility) on new development in Roseville. Authorized under the Mitigation Fee Act - Gov. Code Sec. 66000 et seq. Collected at building permit.

What one house pays

$603

For a typical home: a 2,000 sq ft detached house on a 0.13 acre lot, on a new subdivision lot.

Share of Roseville's total
1%
Total one-time fees here
$82,135
Adjustment
Adjusts yearly · another named index · July
what the document says

annual

Next expected change
1 Jul 2027

The record

Why it exists

“The purpose of the Backbone Mitigation Fee is to prevent existing customers from increased electric rates due to capital expenditures directly related to the addition of customers.”

Roseville Electric Utility, "Final Backbone Mitigation Fee Update", EES Consulting, October 2024, p.1, "INTRODUCTION" · source document ↗
What it pays for

“Electric Backbone Impact Fee: Assessed on each new electric service connection, special service or capacity increase within the City limits, to fund infrastructure facility (substation and 60kV network) improvements, and collected prior to permit issuance.”

"Residential Development Fees, July 2026 — June 2027, Updated July 1, 2026", booklet p.16, "Development Fees & Estimate Worksheet" · source document ↗
Where it applies

“Assessed on each new electric service connection, special service or capacity increase within the City limits”

Residential Development Fees, eff. 7/1/2026, booklet p.16 · source document ↗
When it is paid

at building permit

“and collected prior to permit issuance.”

Residential Development Fees, eff. 7/1/2026, booklet p.16, Electric Backbone Impact Fee · source document ↗
Who collects it

“This booklet provides information about fees applicable to residential development (properties that consist of 1- and 2-family residential units) in the City of Roseville and a worksheet to calculate them. It is published by the Development Services Department and is updated in July each year, to coincide with annual inflationary fee adjustments.”

Residential Development Fees, eff. 7/1/2026, booklet p.1, "Introduction — What is this fee booklet for?" · source document ↗

Every published rate

Land useApplies toBasisEffectiveAmount
—
Single-family detached this home per unit 1 Jul 2026 $603.36

“Electric Backbone Impact Fee: Assessed on each new electric service connection, special service or capacity increase within the City limits, to fund infrastructure facility (substation and 60kV network) improvements, and collected prior to permit issuance. Calculation: Number of units x fee from Table 7 | Table 7 | Land Use | Fee per Unit | Single Family Residential | $603.36”

Residential Development Fees July 2026 — June 2027, Updated July 1, 2026, booklet p.16, Table 7 · source document ↗
none
Multi-family none per unit — $437.44
the line this rate was read from

“Table 7 | Land Use | Fee per Unit | Single Family Residential $603.36 | Multi-Family Residential $437.44”

the levying document · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.