DevFeeFinder
TransportationSet by city fee ordinanceCitation City of Placerville Resolution #9046

Traffic Impact Mitigation Fee

Levied by City of Placerville on new development in Placerville. Authorized under the Mitigation Fee Act - Gov. Code Sec. 66000 et seq. Collected at building permit (fees due at permit issuance).

What one house pays

$20,252

For a typical home: a 2,000 sq ft detached house on a 0.13 acre lot, on a new subdivision lot.

Share of Placerville's total
28%
Total one-time fees here
$71,551
Adjustment
Adjusts yearly · consumer price index
what the document says

CPI annual

Next expected change
1 Jul 2027 rate on file is stale
!

A scheduled adjustment has passed since this rate took effect

This fee escalates annually. The rate on file is effective 14 Apr 2025, and at least one adjustment has fallen due since. The current amount is probably different, and for an indexed fee almost certainly higher. The next change after that is expected 1 Jul 2027.

The figure is published as held rather than projected forward, because a number computed from an index is not a number quoted from an adopted schedule. It is flagged so you can check the agency's current schedule before relying on it.

The record

Why it exists

“The Traffic Impact Mitigation (TIM) Fee Program was developed to equitably spread the costs of traffic and circulation infrastructure needs to those who create the need for such infrastructure. The City Code requires that new development pay a TIM Fee based upon the number of vehicle trips generated by the proposed use.”

Staff Report Item 11.1, 2024-02-27, "Purpose" · source document ↗
What it pays for

“The fees collected by the TIM Fee Program are used to fund transportation improvements needed to accommodate the growth expected by the City's General Plan." / "The projects included in the TIM Fee Program generally include new roadways, road widening projects, and intersection improvements.”

City of Placerville, Traffic Impact Mitigation Fee Program page · source document ↗
When it was adopted

1989 (program established); codified fee schedule adopted 1999-02-23; interim fee ordinance 2006-11-28

“The Traffic Impact Mitigation (TIM) Fee Program was originally established in 1989. It was updated in 1999 and updated again through various actions between 2006 and 2008.”

City Manager's Report, Item 11.1, February 27, 2024, "Background" · source document ↗
Who adopted it

“The Traffic Impact Mitigation (TIM) Fee Program was originally established in 1989. It was updated in 1999 and updated again through various actions between 2006 and 2008.”

City Manager's Report, Item 11.1, February 27, 2024, "Background" · source document ↗
When it is paid

at building permit (fees due at permit issuance)

“Note: All fees for the city and other agencies will be due at issuance. A plan review fee will be determined and become due at time of application. (see fee schedule)”

City of Placerville Single Family Dwelling Application Packet, effective October 7, 2022, rev. 12/12/2022, p. 6, Submittal Checklist note · source document ↗
Who collects it

City of Placerville, the agency that levies it

“In accordance with §66006(a), the City maintains a separate account, the Development Impact Fees Special Revenue Fund, to handle fee payments and disbursements related to this program.”

City Manager's Report, June 23, 2026, "Discussion" · source document ↗
How it changes

“Section 8-15-8 of the City Code includes a provision for the TIM Fee to be adjusted on January 1 of each calendar year by a percentage equal to the inflation rate of construction costs for the prior year. The determination of the inflation rate is based upon the 'Engineering News Record' (ENR) construction cost index.”

Staff Report Item 11.1, 2024-02-27, "Background" · source document ↗

Every published rate

Every rate below applies to single-family detached.

RateBasisEffectiveAmount
this home per DU 14 Apr 2025 $20,252

1 superseded rate on file for this fee and is not shown: they are kept so a figure quoted from an older schedule can still be traced.

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close