Riolo Vineyard Specific Plan Infrastructure Fee

Levied by Placer County (Board of Supervisors); program administered by the County Executive Office / Community Development Resource Agency on new development in Placer County (unincorporated). Authorized under the Mitigation Fee Act - Gov. Code Sec. 66000 et seq. (specific plan area fee). Collected at building permit.

What one house pays

$49,365

This fee is not in Placer County (unincorporated)'s published figure. This site publishes a home outside any plan area, and this charge applies only in Riolo Vineyard. The amount shown is what it costs a house that is there.

Total one-time fees here
$88,997
Adjustment
Not recorded

The record

Why it exists

“The purpose of the Riolo Vineyard Specific Plan Fee Program is to equalize the allocation of costs for the Riolo Vineyard Specific Plan facilities among benefitting properties.”

Exhibit 1, RVSP Fee Program Development Impact Fee Five Year Reporting, FY 2021-2022, § A "Identify the purpose to which the fee is to be put" · source document ↗
What it pays for

“The program contains the following fee components: RVSP Infrastrucutre Facilities Plan Area Fee, the RVSP Supplemental County Facilities Fee, and the RVSP Administration Fee, and contains the following improvements: roadway facilities, sanitary sewer facilities, storm drainage facilities and parks.”

Exhibit 1, Five Year Reporting, § A; sic — "Infrastrucutre" as printed · source document ↗
Where it applies

“The Riolo Vineyard Specific Plan ("RVSP") RVSP Fee Program is a specific development impact fee program applicable only within the RVSP boundaries.”

Placer County Code Art. 15.90, § 15.90.010 Intent; history: Ord. 5898-B § 1, 2017 · source document ↗
When it was adopted

2017-11-14

“The Riolo Vineyard Specific Plan Area ("RVSP") Fee Program was adopted by Ordinance 5898-B on November 14, 2017, in accordance with Section 2.5.5.1 of the Development Agreement for the Riolo Vineyard Specific Plan (Placer County Code, Chapter 15, Article 15.90). The initial fee schedule, supported by a nexus study, was adopted by Resolution 2017-153. A nexus study update was adopted by Resolution 2025-075 on April 15, 2025.”

Riolo Vineyard Specific Plan Area Fee Program, Annual Fiscal Report FY 2024-2025, County Executive Office, January 2026, p. 2, opening paragraph · source document ↗
Who adopted it

Ordinance No. 5898-B (fee program / County Code Art. 15.90); initial fee schedule by Resolution 2017-153

“The Riolo Vineyard Specific Plan Area ("RVSP") Fee Program was adopted by Ordinance 5898-B on November 14, 2017, in accordance with Section 2.5.5.1 of the Development Agreement for the Riolo Vineyard Specific Plan (Placer County Code, Chapter 15, Article 15.90). The initial fee schedule, supported by a nexus study, was adopted by Resolution 2017-153. A nexus study update was adopted by Resolution 2025-075 on April 15, 2025.”

Riolo Vineyard Specific Plan Area Fee Program, Annual Fiscal Report FY 2024-2025, County Executive Office, January 2026, p. 2, opening paragraph · source document ↗
When it is paid

at building permit

“Fee revenue will be collected at the issuance of building permits for development and remaining improvements will be constructed as sufficient fee revenue becomes available.”

RVSP Annual Fiscal Report FY 2024-25, § F, January 2026 · source document ↗
Who collects it

“Riolo Vineyard Specific Plan Area Fee Program ANNUAL FISCAL REPORT FISCAL YEAR 2024-2025 Submitted by County Executive Office”

cover page · source document ↗
Who is exempt

“Ministerial permits issued to a non-participating owner are not subject to the RVSP fee.”

Placer County Code § 15.90.040(D) Exemptions; Ord. 5898-B §1, 2017 · source document ↗
Credits and offsets

“In accordance with Placer County Code Section 15.90.060(C)(1), a fee reimbursement agreement, in a form acceptable to County Counsel, may be entered into between the county and each constructing entity or participating owner in connection with the financing and construction of public improvements identified in the Nexus Study. On August 10, 2021, the Board approved a fee credit/reimbursement agreement with JEN California 8, LLC (JEN) in the amount of $20,783,062.”

CDRA Memorandum, December 14, 2021, "Background"; the same item amends the cap to "$18,035,638" · source document ↗
How it changes

“The Fee Schedule for FY 2025-26 that follows was effective July 1, 2025, and reflects inflationary updates based on the average of the change in the San Francisco CCI and the 20-City Average CCI as reported in the Engineering News Record (ENR).”

RVSP Annual Fiscal Report FY 2024-25, § B "Amount of Fee", January 2026 · source document ↗

Every published rate

Every rate below applies to single-family detached.

RateBasisEffectiveAmount
Riolo Vineyard
per DU 1 Jul 2026 $49,365

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close