Levied by Eastern Municipal Water District on new development in Menifee. Authorized under the Gov. Code Sec. 66013 where the charge is for water or sewer capacity; otherwise the district's own enabling act (Health & Safety Code / Pub. Resources Code, by district type). Collected other: on the Application for Service, as a prerequisite to receiving retail domestic water service; for a residential subdivision tract, re-adjusted and paid in full before the District accepts the facilities and provides service to the unit.

What one house pays

$7,738

For a typical home: a 2,000 sq ft detached house on a 0.13 acre lot, on a new subdivision lot.

Share of Menifee's total
13%
Total one-time fees here
$61,141
Adjustment
Adjusts only when the board sets a new amount
what the document says

by resolution

The record

Why it exists

“Domestic Water System Facilities Financial Participation Charge ("Capacity Charges"/"Connecting Fees") is to provide a source of funds to finance: (1) water main facilities larger than 12-inches in diameter; (2) booster pumping plants; (3) storage tanks; and (4) Improvement District and General District system facilities, as necessary to meet the additional service requirements necessitated by community growth and to distribute the costs fairly among those who create the need for additional facilities.”

EMWD Administrative Code, printed 7/30/24, s. 5.307(a), code p. 325 · source document ↗
What it pays for

“FPCs, sometimes referred to as "connection fees," are collected to pay for planned and existing water and wastewater facilities. • Individuals are required to buy in to these capital facilities. • This buy-in process may include paying toward debt associated with existing facilities. • Some capital facilities include: o Pipelines o Pumping Stations o Wastewater Treatment Plants o Sewage Transmission Lines o Freshwater Connections o Sewage Lift Stations”

Frequently Asked Questions: Financial Participation Charges and Water Supply Development Fee, 1/2026, p. 2, "What are Financial Participation Charges (FPCs)?" · source document ↗
Where it applies

“Are FPCs the same throughout EMWD's service area? • Yes, in most cases, but not all. Customized FPCs have been set in a few areas where EMWD's costs to provide service have differed from standard cost allocations. Customized fees can be higher or lower than the standard, depending on actual, documented construction costs.”

Frequently Asked Questions: Financial Participation Charges and Water Supply Development Fee, 1/2026, p. 2 · source document ↗
When it was adopted

1979-03-14 (by reference only)

“Existing Development Within Improvement Districts: All properties, improved with an existing structure, located within an operating District improvement district providing retail domestic water service prior to the effective date of Resolution 1639 (March 14, 1979), shall be exempt from paying Capacity Charges. Such an exemption shall be applicable whether or not they were receiving domestic water service prior to March 14, 1979.”

EMWD Administrative Code, printed 7/30/24, Title 5 Art. 3 s. 5.307(g)(1), code p. 329 · source document ↗
Who adopted it

Resolution 1639 | NOT FOUND as an affirmative imposing text

“Existing Development Within Improvement Districts: All properties, improved with an existing structure, located within an operating District improvement district providing retail domestic water service prior to the effective date of Resolution 1639 (March 14, 1979), shall be exempt from paying Capacity Charges. Such an exemption shall be applicable whether or not they were receiving domestic water service prior to March 14, 1979.”

EMWD Administrative Code, printed 7/30/24, Title 5 Art. 3 s. 5.307(g)(1), code p. 329 · source document ↗
When it is paid

“Payment of Capacity Charges as a Prerequisite to Receiving Service (1) Through Application for Service: a. New developments and non-exempt existing developments requesting retail domestic water service will be required to pay nonreimbursable Capacity Charges (also known as Financial Participation Charges) shown on the Application for Service.”

EMWD Administrative Code, printed 7/30/24, s. 5.307(b)(1)a, code p. 326 · source document ↗
Who collects it

Eastern Municipal Water District, the agency that levies it

“Service will be commenced after submittal of an application and on payment to the District of the applicable fees, charges and deposits set forth in the Consolidated Schedule of Rates, Fees and Charges as amended from time-to-time by the Board.”

EMWD Administrative Code, printed 7/30/24, s. 5.302, code p. 323 · source document ↗
Who is exempt

“Development to be exempted from Payment of Connection fees: ... (3) Agricultural Use, as defined by the Metropolitan Water District of Southern California Administrative Code, including site specific agricultural operational use and/or functions relative to the product or byproduct of the site use, shall be exempt from paying Capacity Charges. (4) New Recycled water meters, including those that are supplied with potable water sources on an interim basis, shall be exempt from paying capacity charges. (5) ADUs converted from existing space and JADU's shall not be considered to be a new residential use and shall be exempt from connection fees or capacity charges.”

EMWD Administrative Code, printed 7/30/24, s. 5.307(g), code p. 329 · source document ↗
Credits and offsets

“Other Water Connection Fees and Credits — Developer Donated Storage Credit | Rate as of 1/1/2025: ($1,247/EMS) | Rate as of 1/1/2026: ($1,287/EMS)”

Consolidated Schedule of Rates, Fees, and Charges, Updated 7/15/2026, p. 60, "CONNECTION FEES — Water Connection Fees: — Other Water Connection Fees and Credits" · source document ↗

Every published rate

Every rate below applies to single-family detached.

RateBasisEffectiveAmount
General District
this home per EDU 1 Jan 2026 $7,738

“SINGLE RESIDENTIAL LOT WITHOUT RESIDENTIAL FIRE SPRINKLERS - DOMESTIC WATER METERS — Minimum Lateral Size(1) 1" | Meter Type Master Meter Multi-Jet | Meter Size 5/8" | Maximum Continuous Capacity (GPM) 15 | Equivalent Meter Size (EMS) Factor (2)(3) 1.00 | Water Financial Participation Charges $7,738.00”

EMWD "Water Meters and Associated Meter Fees and Connection Fees", header "JANUARY 1, 2026 RATES", p. 1, first residential table · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close