The record
“Updating the Eastside Bridge and Major Thoroughfare Construction Fee District, hereinafter referred to as 'District', will provide an equitable financing mechanism by which new development within an identified area will share the costs of providing full mitigation improvements.”
“to defray the cost of constructing bridges over waterways, railways, freeways, and canyons, and/or constructing major thoroughfares”
“The District includes the existing Canyon Country community and lies generally within the Friendly Valley, Mint Canyon, Sand Canyon, and Vasquez Canyon areas of the Santa Clarita Valley.”
1982-03-02 (County enabling code); district itself 1987-07-21
“The Los Angeles County Board of Supervisors adopted Ordinance No. 82-0050 on March 2, 1982, adding Section 21.32.200 to the Los Angeles County Code.”
“The Los Angeles County Board of Supervisors adopted Ordinance No. 82-0050 on March 2, 1982, adding Section 21.32.200 to the Los Angeles County Code.”
other: at recordation of a final map, or just prior to issuance of a building permit (whichever applies)
“The District fee is collected at the time of recordation of a final map or just prior to the issuance of a building permit." and, for non-residential without a land division, "fees shall be paid prior to the issuance of a building permit.”
“The County or City will maintain a separate District Fund for the Eastside District. Funds may be loaned to or from the Eastside District provided that the loans are properly recorded by no less than a Resolution approved by the County Board of Supervisors.”
“A zoning designation of OS (open space) is not subject to B&T District Fee”
“If a developer constructs District-identified improvements prior to map recordation, that developer becomes eligible for District credit which can be used to offset District fee payments." / "If a condition of project approval requires a landowner to dedicate property as right of way for a State improvement, then the landowner will receive credit at fair market value." / "if right-of-way is required to be dedicated for a County improvement, as a condition of project approval, the landowner receives no credit." / "In the event that District fees collected from developers exceed the cost of improvements, the surplus funds, less administrative costs, will be refunded at District closure by the City and/or County to current owners in proportion to District fees paid.”
“Fees are subject to change, and are based on the current rate at the time of payment”
Every published rate
| Land use | Applies to | Basis | Effective | Amount |
|---|---|---|---|---|
| Eastside (Canyon Country) | ||||
| Single-family detached | this home | per DU | 14 Nov 2024 | $23,980 |
| Multi-family | townhome/condo | per DU | 14 Nov 2024 | $19,190 |
| Multi-family | apartment | per DU | 14 Nov 2024 | $16,790 |
3 superseded rates on file for this fee and are not shown: they are kept so a figure quoted from an older schedule can still be traced.