Levied by City of Lathrop on new development in Lathrop. Authorized under the Mitigation Fee Act - Gov. Code Sec. 66000 et seq. Collected at building permit.

Not priced for this house. This charge is real, adopted and collected, and it is left out of Lathrop's figure for one reason: it is levied as a percentage of another fee, and a typical home does not fix that quantity. That is not the same as a zero. The fee is owed; what is missing is the number to multiply by, and inventing one would price this house with more confidence and less truth. Every published rate is in the table below.

The record

Why it exists

“Under Government Code Section 66000 et seq., the City is required to separately account for revenues and expenditures within the capital facilities fee funds and is allowed to apply an appropriate fee for administration of Transportation, Municipal Services, Culture and Leisure, and Regional Levee Fees as identified in the report titled "City of Lathrop Capital Facilities Fees, As Amended September 2, 2003" and the "Mossdale Tract Area Regional Urban Level of Flood Protection Levee Impact Fee, Nexus Study, Adopted by SJAFCA, Resolution No. 18-21, November 8, 2018".”

Capital Facility Fee Funds Report 2024-2025, report period July 1, 2024 to June 30, 2025; "Administration Capital Facility Fee – 2290", s. 1.a, Page 18 · source document ↗
What it pays for

“A total of $100,000 was transferred from Fund 2290 to cover the Capital Facility Fee Program administration costs. • $100,000 was transferred to the Admin Services, General Fund.”

Capital Facility Fee Funds Report 2024-2025; "Administration Capital Facility Fee – 2290", s. 2.b, Page 19 · source document ↗
Where it applies

3.0% citywide, except the Crossroads area, which levies 1.0% under its Development Agreement

“The City also levies a 3.0% administration fee to the cumulative total of all its CFFs, excluding CFFs charged to the Crossroads area which levies a 1.0% administration fee. The administration fee pays for the administrative duties associated with the CFF program. This 3.0% administration fee (or 1.0% for Crossroads) would be added on top of the City CFFs presented in Table ES-1.”

City of Lathrop 2024 Capital Facilities Fee Study Update (Goodwin Consulting Group), Executive Summary, "FEE SCHEDULE", p. viii = PDF p. 12 · source document ↗
When it is paid

at building permit

“This fee is calculated as a percentage of the capital facilities fees charged prior to issuance of the building permit. Currently the fee is 3% of all capital facility fees applicable to the project.”

Capital Facility Fee Funds Report 2024-2025; "Administration Capital Facility Fee – 2290", s. 1.b "Amount of Fee", Page 18 · source document ↗
Who collects it

City of Lathrop, the agency that levies it

“City of Lathrop / Department of Public Works / (209) 941-7430 ... REQUEST FOR BUILDING PERMIT AND DEVELOPMENT IMPACT FEE ESTIMATE: One and Two Family Residential ... The estimate provided is not an invoice; fees will be invoiced prior to building permit issuance.”

Request for Building Permit and Development Impact Fee Estimate, One and Two Family Residential, 1 page, undated on its face · source document ↗
Credits and offsets

The base is stated as "ALL CFF FEES AND CREDITS" and no document read says what that means. NOT SETTLED.

“ADD 3% ADMINISTRATIVE FEE TO CUMULATIVE TOTAL OF ALL CFF FEES AND CREDITS EXCLUDING THE SAN JOAQUIN RTIF AND LEVEE IMPACT”

Capital Facilities Fee Schedule effective July 1, 2026, the administrative line as printed on eight of the twelve area pages · source document ↗

Every published rate

RateBasisEffectiveAmount
East Lathrop / North Harlan ID / Mossdale Village / Mossdale Landings / SLSP-SLCC / SLSP-Non SLCC / Lathrop Gateway BP / Ag Mitigation-Other
percent 1 Jul 2026 $3.00
the line this rate was read from

“ADD 3% ADMINISTRATIVE FEE TO CUMULATIVE TOTAL OF ALL CFF FEES AND CREDITS EXCLUDING THE SAN JOAQUIN RTIF AND LEVEE IMPACT”

Capital Facilities Fee Schedule effective July 1, 2026, sha256 24b0a350..., the line below each area fee table on file pages 3 (EAST LATHROP), 5 (NORTH HARLAN IMPROVEMENT DISTRICT), 8 (MOSSDALE VILLAGE), 10 (MOSSDALE LANDINGS), 15 (SLSP - SLCC), 17 (SLSP - Non SLCC), 19 (LATHROP GATEWAY BUSINESS PARK SPECIFIC PLAN) and 21 (AG MITIGATION FEE - OTHER), identically worded · source document ↗
Stewart Tract / North Lathrop Transportation Impact Fee
percent 1 Jul 2026 $3.00
the line this rate was read from

“ADD 3% ADMINISTRATIVE FEE TO CUMULATIVE TOTAL OF ALL CFF FEES AND CREDITS EXCLUDING THE SAN JOAQUIN RTIF”

Capital Facilities Fee Schedule effective July 1, 2026, sha256 24b0a350..., file pages 13 (STEWART TRACT) and 20 (NORTH LATHROP TRANSPORTATION IMPACT FEE) · source document ↗
Central Lathrop Phase I and II
percent 1 Jul 2026 $3.00
the line this rate was read from

“ADD 3% ADMINISTRATIVE FEE TO CUMULATIVE TOTAL OF ALL CFF FEES AND CREDITS EXCLUDING THE SAN JOAQUIN RTIF, LEVEE IMPACT, AND CITY REIMBURSEMENT”

Capital Facilities Fee Schedule effective July 1, 2026, sha256 24b0a350..., file page 12 (CENTRAL LATHROP PHASE I AND II) · source document ↗
Crossroads Business Park
percent 1 Jul 2026 $1.00
the line this rate was read from

“ADD 1% ADMINISTRATIVE FEE TO CUMULATIVE TOTAL OF ALL CFF FEES per Development Agreement EXCLUDING LEVEE IMPACT”

Capital Facilities Fee Schedule effective July 1, 2026, sha256 24b0a350..., file page 6 (CROSSROADS BUSINESS PARK) · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.