What one house pays

$1,347

This fee is not in Folsom's published figure. This site publishes a home outside any plan area, and this charge applies only in Folsom Plan Area. The amount shown is what it costs a house that is there.

Total one-time fees here
$69,319
Adjustment
Adjusts yearly · ENR construction cost index · July
what the document says

ENR-CCI annual

Next expected change
1 Jul 2027

The record

Why it exists

“The city council finds and declares that the purposes of this chapter are as follows: A. Proposed developments in the Folsom plan area create a need for additional public improvements, infrastructure, facilities and services with the addition of residents, businesses, and visitors.”

Folsom Municipal Code s. 3.120.010 Purpose and finding, subsection A · source document ↗
What it pays for

“The fire component of the FPASP fee is to fund two new fire stations to serve the Folsom plan area, as described in the PFFP and the nexus study.”

Folsom Municipal Code s. 3.120.060 Components of the FPA development impact fee, subsection G(5) · source document ↗
Where it applies

“\u201cFolsom plan area\u201d (FPA) means the property within the city of Folsom located south of Highway 50 within the Folsom plan area specific plan adopted by the city council on June 28, 2011, in Resolution No. 8863.”

Folsom Municipal Code s. 3.120.020 Definitions, subsection J · source document ↗
When it was adopted

2015

“This chapter shall apply to all new development projects in the Folsom plan area. (Ord. 1234 § 2 (part), 2015)”

Folsom Municipal Code Chapter 3.120, FOLSOM PLAN AREA DEVELOPMENT IMPACT FEES, s. 3.120.030 Application of chapter; codified ordinance history Ord. 1234 § 2 (part), 2015 · source document ↗
Who adopted it

Ordinance No. 1234

“This chapter shall apply to all new development projects in the Folsom plan area. (Ord. 1234 § 2 (part), 2015)”

Folsom Municipal Code Chapter 3.120, FOLSOM PLAN AREA DEVELOPMENT IMPACT FEES, s. 3.120.030 Application of chapter; codified ordinance history Ord. 1234 § 2 (part), 2015 · source document ↗
When it is paid

at building permit

“The developer of any new development in the Folsom plan area shall pay the FPA development impact fee at or prior to the issuance of any building permit for a structure which is subject to this chapter. The amount of the fee shall be the then-current amount at the time of the building permit issuance, and shall be paid on a building-permit-by-building-permit basis.”

Folsom Municipal Code s. 3.120.050 Payment of the FPA development impact fee · source document ↗
Who collects it

City of Folsom, the agency that levies it

“City of Folsom / Community Development Department / 50 Natoma Street / Folsom, CA 95630 / 916-461-6200 … FOLSOM PLAN AREA DEVELOPMENT IMPACT FEES AND PERMIT FEES … Effective July 1, 2026”

"Folsom Plan Area Development Impact Fees and Permit Fees", sheet dated 7/21/2026, page 1 masthead · source document ↗
Who is exempt

“\u201cDevelopment\u201d means the construction of any new structure in the Folsom plan area, including residential and nonresidential structures. Development does not include, with respect to residential development, remodeling, reconstruction or expansion of a structure that does not increase the number of unit(s) on the parcel…”

Folsom Municipal Code s. 3.120.020 Definitions, subsection E · source document ↗
Credits and offsets

“Fee credits related to improvements or equipment financed by the FPASP component of the FPA development impact fee may not be applied against any of the other components of the FPA development impact fee. Similarly, fee credits related to improvements or equipment financed by any other component of the FPA development impact fee may only be applied against that particular component of the FPA development impact fee.”

Folsom Municipal Code s. 3.120.100 Fee reimbursement agreements, subsection C · source document ↗

Every published rate

Land useApplies toBasisEffectiveAmount
Folsom Plan Area
Single-family detached SFLD low density per DU 1 Jul 2026 $1,347
the line this rate was read from

“Impact Fees for Folsom Plan Area Residential based on Zoning | Zoning | Applied per Unit | SFLD … 1. Specific Plan Fees … E Fire $ 1,347”

"Folsom Plan Area Development Impact Fees and Permit Fees", effective 7/1/2026, sheet dated 7/21/2026, page 3, section "1. Specific Plan Fees", lettered row E, SFLD column · source document ↗
Multi-family MLD per unit — $1,303
the line this rate was read from

“Impact Fees for Folsom Plan Area Residential based on Zoning | Zoning | Applied per Unit | MLD … 1. Specific Plan Fees … E Fire $ 1,303”

the levying document · source document ↗
Multi-family MMD per unit — $1,303
the line this rate was read from

“Impact Fees for Folsom Plan Area Residential based on Zoning | Zoning | Applied per Unit | MMD … 1. Specific Plan Fees … E Fire $ 1,303”

the levying document · source document ↗
Multi-family MHD per unit — $1,303
the line this rate was read from

“Impact Fees for Folsom Plan Area Residential based on Zoning | Zoning | Applied per Unit | MHD … 1. Specific Plan Fees … E Fire $ 1,303”

the levying document · source document ↗
Multi-family MU-R per unit — $1,303
the line this rate was read from

“Impact Fees for Folsom Plan Area Residential based on Zoning | Zoning | Applied per Unit | MU-R … 1. Specific Plan Fees … E Fire $ 1,303”

the levying document · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close